Budget and Timeline

The major portion of budget is required for setup cost of hospital building, equipment’s, Pharmacy, laboratory and digitization of hospital.
  • Starts from 2019 April Phase 1 :

    Will operate two sub phase (a) and (b) Sub-phase (a): building a complete Out Patients’ Department (OPD), hospital administration offices, with X ray, USG and minor Emergency Services, Pharmacy and minor laboratory service. MBBS doctor will be in charge of curative care. Sub-phase (b): addition of ward and emergency to (a). Total cost estimated: 74 lakhs Phase I start from the existing Ayurvedic building which cost around 74 lakhs, which will be handed over by Municipality.
  • Starts from 2020 April Phase 2 :

    Shift to own Building at Gautu Addition of Maternity services Total cost cumulative estimated:374 plus
  • Starts from 2021 AprilPhase 3 :

    Addition of operating theatres, Ambulance, complete Digitalization. MDGP doctor will take in charge of curative care. Complete 15 bed digital rural community hospital. Total cost cumulative estimated: 854 lakhs